Error - 'Invalid Project' when selecting a project on an expense that definitely exists in Dimensions

Clear all fields on the detail line of the transaction — Analysis Code, Cost Centre, and Project Code. Then repopulate them one by one. The fields can depend on each other, and if one has been changed, this can cause the error. Once all fields are cleared and repopulated, the error should no longer appear. If this does not resolve the issue, the project may have been set up directly in Dimensions rather than through FocalPoint. When using standard functionality, projects must be set up through FocalPoint's Project Commencement screen. If they are only in the Dimensions tables and not the FocalPoint ones, this error appears. If you have custom functionality to create project records — such as a Workflow Form or a third-party integration — this may differ. For further assistance, see Get support in FocalPoint.